Title
2024 Pavement Improvement Project, CIP 9981.
Recommended Action
Approve a Resolution approving the plans and specifications for the 2024 Pavement Improvement Project, CIP 9981; awarding a contract to Granite Rock Company for the 2024 Pavement Improvement Project, CIP 9981 in the amount of $5,387,979.50; authorize a 25% contingency for the 2024 Pavement Improvement Project, CIP 9981; and authorizing the Interim City Manager to execute all necessary documents and approvals related to additional work, via contract change orders in an amount not to exceed $1,340,000.