File #: ID#24-670    Version: 1 Name:
Type: Resolution Status: Passed
File created: 11/13/2024 In control: City Council
On agenda: 11/19/2024 Final action: 11/19/2024
Title: Boronda Road Congestion Relief Project Phase 1, CIP No. 9510 - CCOs
Attachments: 1. Staff Report - CCOs - Boronda Road Project Phase 1, 2. Resolution - CCOs for CIP 9510 - Boronda Rd - Ph 1, 3. Exhibit A for CCO No 2

Title

Boronda Road Congestion Relief Project Phase 1, CIP No. 9510 - CCOs

Recommended Action

Approve a Resolution approving Contract Change Order (CCO) No. 2 for the Boronda Road Congestion Relief Project Phase 1, CIP No. 9510 in the amount of $180,000; approving 12% project contingencies in the amount of $1,876,536 for this project for a revised not to exceed total construction costs amount of $17,514,332.93; and authorizing the City Manager to approve all change orders for this project.