Award of the Closter Park Revitalization Project No. 9350, 2018 Parks Bond Act Grant Recipient Project No. SW-27-006
Recommended Action
Approve a Resolution approving the Plans and Specifications for the Closter Park Revitalization Project No. 9350, 2018 Parks Bond Act Grant Recipient Project No. SW-27-006; and awarding a contract to McGuire and Hester for the Closter Park Revitalization, Project No. 9350, in an amount not to exceed $6,915,983 and authorizing the Mayor to execute the contract on behalf of the City; and authorizing the Public Works Director or his designee to approve contract change orders up to an additional 6% of the contract amount, $415,000, for construction contingencies; and approving the reallocation of $280,000 from CIP 9048 and $20,000 from CIP 9022 to CIP 9350.