File #: ID#23-724    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 11/16/2023 In control: City Council
On agenda: 12/5/2023 Final action:
Title: City Hall First Floor Build Back, Project No. 8170
Attachments: 1. Staff Report - City Hall 1st Floor Build Back.pdf, 2. Resolution - City Hall 1st Floor Build Back.pdf

Title

City Hall First Floor Build Back, Project No. 8170

Recommended Action

Approve a Resolution approving the Plans and Specifications for the City Hall First Floor Build Back, CIP No. 8170; and awarding a contract to Premier Builders, Inc. for the City Hall First Floor Build Back, CIP No. 8170 in the amount of $1,859,138; and authorizing 25% of the contract amount, $464,784.50, for construction contingencies for the City Hall First Floor Build Back, CIP No. 8170; and approving the City’s reallocation of American Rescue Plan Act funds (ARPA), in the amount of $1,000,000, from Park Irrigation Upgrades (3911.55.8191) to Adaptations to City Hall project (3911.50.8170).